Note: For certain projects, the City allocated funds through multiple sub-categories. BGR grouped these allocations into singular projects to help residents understand the full scope and funding. As such, the totals for the sub-categories are different than those in the Beyond the Ballot report. The totals for the main categories (Public Facilities and Equipment, Infrastructure, Affordable Housing, and Project Management) align with those in the report.
*The City indicated that it has deposited these funds in the Housing Trust Fund.
| Project | Category | Sub-Category | Total Appropriations (2021 and 2024 Bonds) | Total Expenditures (2021 and 2024 Bonds) | Percentage Spent | ||||
|---|---|---|---|---|---|---|---|---|---|
| Phase III - Orleans Parish Jail Medical and Mental Health Facility | Public Facilities and Equipment | Public Safety and Justice System | $ 50,139,342 | $ 46,667,066 | 93.1% | ||||
| Sewerage & Water Board Power Plant | Infrastructure | Sewerage & Water Board Power Complex | $ 37,878,371 | $ 37,878,371 | 100% | ||||
| Gordon Plaza Settlement and Redevelopment | Public Facilities and Equipment | Gordon Plaza Settlement and Redevelopment | $ 31,642,918 | $ 27,504,896 | 86.9% | ||||
| Municipal and Traffic Court Renovations | Public Facilities and Equipment | Public Safety and Justice System | $ 28,842,769 | $ 17,544,623 | 60.8% | ||||
| Street Lights, Signs and Traffic Signals (Streets) | Infrastructure | Streets and Rights of Way | $ 20,715,511 | $ 13,525,412 | 65.3% | ||||
| Charity Hospital Redevelopment | Public Facilities and Equipment | Charity Hospital Redevelopment | $ 20,000,000 | $ - | 0% | ||||
| Audubon Institute (Riverfront for All, Park and Stormwater Projects) | Public Facilities and Equipment | Parks and Recreation | $ 17,481,108 | $ 15,760,000 | 90.2% | ||||
| Available Bond Funds* | Affordable Housing | Affordable Housing | $ 17,197,819 | $ - | 0% | ||||
| Emergency Response Vehicles and Heavy Equipment Replacement | Public Facilities and Equipment | Public Safety and Justice System | $ 16,784,871 | $ 9,829,584 | 58.6% | ||||
| Lincoln Beach Redevelopment | Infrastructure | Lincoln Beach Redevelopment | $ 16,442,252 | $ 7,049,943 | 42.9% | ||||
| Project Management - Bond Funds | Project Management | City Administration | $ 16,005,476 | $ 8,231,373 | 51.4% | ||||
| Gap Financing | Affordable Housing | Affordable Housing | $ 14,800,000 | $ 14,224,250 | 96.1% | ||||
| Citywide ROW Asphalt Improvements | Infrastructure | Streets and Rights of Way | $ 11,731,985 | $ - | 0% | ||||
| ROW Improvements - District D & CBD | Infrastructure | Streets and Rights of Way | $ 10,652,920 | $ 10,652,920 | 100% | ||||
| French Quarter ROW Improvements 2024 | Infrastructure | Streets and Rights of Way | $ 10,000,000 | $ 7,760,065 | 77.6% | ||||
| Sanitation Field Operations Office and Warehouse | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 9,954,343 | $ 5,502,666 | 55.3% | ||||
| Central Business District ROW Improvements | Infrastructure | Streets and Rights of Way | $ 9,932,777 | $ 6,633,007 | 66.8% | ||||
| Citywide Building Repairs (2021-2027) | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 9,910,600 | $ 6,505,979 | 65.6% | ||||
| Camp (Valmont - Jefferson), Chestnut/Coliseum (Valmont - Leontine), Leontine/Valmont (Mag-Prytania) | Infrastructure | Streets and Rights of Way | $ 8,399,364 | $ 8,399,364 | 100% | ||||
| Citywide ROW Concrete Improvements | Infrastructure | Streets and Rights of Way | $ 8,248,748 | $ - | 0% | ||||
| Pontalba Apartments Renovations | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 8,000,000 | $ 8,000,000 | 100% | ||||
| Bond Sale Administration - Percent for Art Program | Project Management | Percent for Art Program | $ 7,470,708 | $ 7,193,779 | 96.3% | ||||
| Drainage Pump Station 01 Watershed Drainage Improvements (Broadmoor) Phase I | Infrastructure | Stormwater Management | $ 6,951,093 | $ 2,981,686 | 42.9% | ||||
| Morris F.X. Jeff Sr. Park Renovations (Natatorium and Softball Fields) | Public Facilities and Equipment | Parks and Recreation | $ 6,848,640 | $ 6,319,697 | 92.3% | ||||
| NOFD Headquarters (MTA Building - City Park) | Public Facilities and Equipment | Public Safety and Justice System | $ 6,664,686 | $ 5,274,299 | 79.1% | ||||
| Convention Center / River District ROW | Infrastructure | Streets and Rights of Way | $ 6,253,652 | $ - | 0% | ||||
| Sewerage & Water Board Repaving (Stormwater) | Infrastructure | Stormwater Management | $ 6,188,863 | $ 6,188,863 | 100% | ||||
| Touro-Shakspeare Stabilization | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 6,000,000 | $ 4,589,091 | 76.5% | ||||
| Temporary Detention Center Renovations | Public Facilities and Equipment | Public Safety and Justice System | $ 5,867,704 | $ 5,867,704 | 100% | ||||
| Bayou St. John Infrastructure Improvements | Infrastructure | Streets and Rights of Way | $ 5,736,387 | $ 5,736,387 | 100% | ||||
| Skelly Rupp Stadium Repairs | Public Facilities and Equipment | Parks and Recreation | $ 5,550,070 | $ 5,481,382 | 98.8% | ||||
| Bourbon St. Bollard Assessment and Replacement | Infrastructure | Streets and Rights of Way | $ 5,298,942 | $ 2,566,846 | 48.4% | ||||
| Municipal Auditorium Redevelopment | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 5,000,000 | $ - | 0% | ||||
| Morrison Road Phases I and II | Infrastructure | Streets and Rights of Way | $ 4,873,276 | $ 542,575 | 11.1% | ||||
| Hard Rock Hotel Collapse Infrastructure Repairs | Infrastructure | Streets and Rights of Way | $ 4,706,832 | $ 4,368,720 | 92.8% | ||||
| Camp St. (Louisiana - Washington Ave) | Infrastructure | Streets and Rights of Way | $ 4,584,677 | $ 4,584,677 | 100% | ||||
| Projects related to the Joint Infrastructure Recovery Request (JIRR) program | Infrastructure | Streets and Rights of Way | $ 4,474,256 | $ 4,442,571 | 99.3% | ||||
| Drainage Improvements (Hurricane Isaac Drain Point Repairs Phase II) | Infrastructure | Stormwater Management | $ 4,145,307 | $ 3,853,555 | 93% | ||||
| Asset Management System (Facilities and Equipment) | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 3,916,937 | $ 2,750,705 | 70.2% | ||||
| City Hall/Civil Court Upgrades/Repairs | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 3,775,798 | $ 3,774,359 | 100% | ||||
| Citywide Life/Safety Upgrades and Repairs | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 3,763,088 | $ 304,554 | 8.1% | ||||
| Downtown Development District Drainage Improvements | Infrastructure | Stormwater Management | $ 3,561,174 | $ 444,789 | 12.5% | ||||
| Super Bowl Turf Installation | Public Facilities and Equipment | Parks and Recreation | $ 3,517,555 | $ 2,391,079 | 68% | ||||
| New NOPD Firing Range | Public Facilities and Equipment | Public Safety and Justice System | $ 3,376,713 | $ 3,376,713 | 100% | ||||
| Lakeview Alleyways Reconstruction | Infrastructure | Streets and Rights of Way | $ 3,325,110 | $ 3,325,110 | 100% | ||||
| Department of Public Works Vehicles and Heavy Equipment | Infrastructure | Streets and Rights of Way | $ 3,170,814 | $ 2,977,055 | 93.9% | ||||
| Sanitation Vehicle and Heavy Equipment Replacement | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 3,112,759 | $ 1,536,472 | 49.4% | ||||
| Fleet Management System | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 2,799,974 | $ 2,799,974 | 100% | ||||
| St. Roch Drainage | Infrastructure | Stormwater Management | $ 2,777,231 | $ 2,340,443 | 84.3% | ||||
| Earhart Blvd Food Truck Court | Infrastructure | Streets and Rights of Way | $ 2,685,697 | $ 2,685,697 | 100% | ||||
| Infrastructure Staff Augmentation FEMA Project Management | Project Management | City Administration | $ 2,619,641 | $ 1,970,111 | 75.2% | ||||
| Parent Codes & Citywide Funding | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 2,591,977 | $ - | 0% | ||||
| Tier 2 Radio System | Public Facilities and Equipment | Public Safety and Justice System | $ 2,500,000 | $ 2,500,000 | 100% | ||||
| Sam Bonart Park Expansion | Public Facilities and Equipment | Parks and Recreation | $ 2,500,000 | $ - | 0% | ||||
| Old VA Hospital Renovations and Rehabilitation | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 2,323,839 | $ 373,421 | 16.1% | ||||
| Public Safety Warehouse Acquisition | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 2,271,927 | $ 2,271,927 | 100% | ||||
| Box Culvert Repairs (2500 Orleans Ave & Perrier & Webster) | Infrastructure | Stormwater Management | $ 2,007,360 | $ 2,007,360 | 100% | ||||
| Gardena Dr (St. Bernard Ave - Paris Ave.) | Infrastructure | Streets and Rights of Way | $ 1,923,335 | $ 1,923,335 | 100% | ||||
| Mosquito, Termite and Rodent Control Board Equiment and Renovations | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 1,881,341 | $ 1,703,185 | 90.5% | ||||
| ROW Improvements - District E | Infrastructure | Streets and Rights of Way | $ 1,790,938 | $ 1,790,938 | 100% | ||||
| Parks & Parkways Vehicle and Heavy Equipment Replacement | Public Facilities and Equipment | Parks and Recreation | $ 1,789,362 | $ 1,748,074 | 97.7% | ||||
| ROW Improvements - District A | Infrastructure | Streets and Rights of Way | $ 1,565,048 | $ 1,565,048 | 100% | ||||
| Almonaster St. Bridge Rehabilitiation | Infrastructure | Streets and Rights of Way | $ 1,500,000 | $ - | 0% | ||||
| Citywide Greenspace Restoration | Public Facilities and Equipment | Parks and Recreation | $ 1,425,573 | $ 188,482 | 13.2% | ||||
| Uptown Quiet Zones | Infrastructure | Streets and Rights of Way | $ 1,388,000 | $ - | 0% | ||||
| Canal Blvd. Reconstruction (RE.Lee - Amethyst) | Infrastructure | Streets and Rights of Way | $ 1,281,108 | $ 1,281,108 | 100% | ||||
| NOPD 8th District Police Station Renovations | Public Facilities and Equipment | Public Safety and Justice System | $ 1,264,018 | $ 616,664 | 48.8% | ||||
| Criminal District Court Renovations | Public Facilities and Equipment | Public Safety and Justice System | $ 1,219,124 | $ 268,609 | 22% | ||||
| Ground Transportation Bureau Administration & Inspection Site (formerly N.O. East Brake Tag Station) | Public Facilities and Equipment | Public Safety and Justice System | $ 1,203,468 | $ 3,468 | 0.3% | ||||
| Climate Pollution Reduction - Municipal Building Decarbonization | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 1,174,611 | $ - | 0% | ||||
| Private LTE Network - Fiber Broadband | Public Facilities and Equipment | Public Safety and Justice System | $ 1,144,342 | $ 798,026 | 69.7% | ||||
| Infrastructure Program Management Services | Project Management | City Administration | $ 1,135,468 | $ 1,135,468 | 100% | ||||
| Claiborne Corridor Phase I (Parks and Recreation) | Public Facilities and Equipment | Parks and Recreation | $ 1,124,715 | $ 1,122,897 | 99.8% | ||||
| Citywide HML, Playground Equipment Replacement, HVAC Replacement, Playground Safety Surface and Renovations | Public Facilities and Equipment | Parks and Recreation | $ 1,081,396 | $ 759,409 | 70.2% | ||||
| New Orleans Museum of Art Katrina Repairs (Phase II) | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 1,070,000 | $ 932,026 | 87.1% | ||||
| Union Passenger Terminal Repairs | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 1,054,949 | $ 878,077 | 83.2% | ||||
| Drainage Studies (Lakeview, Mid-City, City Park, Navarre and West End) | Infrastructure | Stormwater Management | $ 1,045,820 | $ 962,319 | 92% | ||||
| Public Safety Cameras | Public Facilities and Equipment | Public Safety and Justice System | $ 1,030,849 | $ 530,849 | 51.5% | ||||
| Alvar St. to Florida Truck Route Clearing and Restoration | Infrastructure | Streets and Rights of Way | $ 1,000,000 | $ - | 0% | ||||
| Holiday Dr. Bridge @ Algiers Canal | Infrastructure | Streets and Rights of Way | $ 989,218 | $ - | 0% | ||||
| Citywide Tree Planting | Public Facilities and Equipment | Parks and Recreation | $ 956,538 | $ 956,538 | 100% | ||||
| NOFD Engine 07 Katrina Repairs | Public Facilities and Equipment | Public Safety and Justice System | $ 930,228 | $ 462,704 | 49.7% | ||||
| Criminal Evidence & Processing Complex | Public Facilities and Equipment | Public Safety and Justice System | $ 848,817 | $ 848,817 | 100% | ||||
| Village de L'est Splash Pad | Public Facilities and Equipment | Parks and Recreation | $ 847,891 | $ 34,414 | 4.1% | ||||
| Perry Roehm Stadium Renovations | Public Facilities and Equipment | Parks and Recreation | $ 838,186 | $ 12,590 | 1.5% | ||||
| Magazine St. Phase II (Nashville-East Dr.) | Infrastructure | Streets and Rights of Way | $ 801,327 | $ 143,736 | 17.9% | ||||
| Andrew Higgins Drive Streetscape (Magazine-Convention Ctr) | Infrastructure | Streets and Rights of Way | $ 800,000 | $ - | 0% | ||||
| Loyola Interchange - Airport Cooperative Endeavor Agreement | Infrastructure | Streets and Rights of Way | $ 800,000 | $ 400,000 | 50% | ||||
| New Orleans Public Library Miscellaneous Repairs and Renovations | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 795,000 | $ 219,657 | 27.6% | ||||
| Lafitte Greenway Extension & Corridor Bike Path | Infrastructure | Streets and Rights of Way | $ 771,200 | $ 191,566 | 24.8% | ||||
| Mirabeau Garden Stormwater Management and Flood Mitigation | Infrastructure | Stormwater Management | $ 750,000 | $ 494,313 | 65.9% | ||||
| Octavia (Freret - Claiborne) | Infrastructure | Streets and Rights of Way | $ 713,421 | $ 713,421 | 100% | ||||
| Citywide Cemetery Restoration | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 699,602 | $ 123,390 | 17.6% | ||||
| School Signs & Flashing Signal Beacon Upgrades | Infrastructure | Streets and Rights of Way | $ 694,465 | $ 35,675 | 5.1% | ||||
| Juvenile Justice Intervention Center Upgrades | Public Facilities and Equipment | Public Safety and Justice System | $ 689,997 | $ 337,355 | 48.9% | ||||
| NOFD Multi Station Renovations | Public Facilities and Equipment | Public Safety and Justice System | $ 659,514 | $ 523,498 | 79.4% | ||||
| Parks and Parkways Forestry Building Upgrades | Public Facilities and Equipment | Parks and Recreation | $ 657,604 | $ 25,939 | 3.9% | ||||
| Conti St. (Bourbon-Chartres) | Infrastructure | Streets and Rights of Way | $ 651,545 | $ 224,608 | 34.5% | ||||
| 1340 Poydras Build-Out OBES | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 650,000 | $ 650,000 | 100% | ||||
| Sewerage & Water Board Repaving (Streets) | Infrastructure | Streets and Rights of Way | $ 648,097 | $ 648,097 | 100% | ||||
| Sanchez (Copelin-Byrd) Center HVAC Repairs | Public Facilities and Equipment | Parks and Recreation | $ 600,000 | $ 560,500 | 93.4% | ||||
| Public Litter & Recycling Cans | Public Facilities and Equipment | Public Safety and Justice System | $ 589,702 | $ 589,702 | 100% | ||||
| Gordon Plaza Settlement and Redevelopment (Streets) | Infrastructure | Streets and Rights of Way | $ 563,353 | $ 475,952 | 84.5% | ||||
| Claiborne Corridor Phase I (Streets) | Infrastructure | Streets and Rights of Way | $ 553,046 | $ 553,046 | 100% | ||||
| French Market Public Restroom Renovation | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 550,000 | $ 550,000 | 100% | ||||
| NOPD 1st District Police Station Repairs | Public Facilities and Equipment | Public Safety and Justice System | $ 522,744 | $ 518,002 | 99.1% | ||||
| ROW Improvements - District C | Infrastructure | Streets and Rights of Way | $ 504,643 | $ 504,643 | 100% | ||||
| New Orleans East I-10 Service Rd. Water Main Installation | Infrastructure | Streets and Rights of Way | $ 500,000 | $ - | 0% | ||||
| Green Infrastructure Maintenance Tool Kit | Infrastructure | Stormwater Management | $ 481,695 | $ 437,458 | 90.8% | ||||
| Gernon Brown Play Structure & Werner Playground Basketball Court Refurbishment | Public Facilities and Equipment | Parks and Recreation | $ 463,765 | $ 451,616 | 97.4% | ||||
| Upper Ninth Ward Community Flood Mitigation | Infrastructure | Stormwater Management | $ 444,310 | $ - | 0% | ||||
| New Orleans East Radio Tower Emergency Backup Power | Public Facilities and Equipment | Public Safety and Justice System | $ 427,969 | $ 427,969 | 100% | ||||
| 2020-2021 Property Management Capital Fund Requests | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 403,092 | $ 403,092 | 100% | ||||
| Goretti Park Playground Area and Play Structure | Public Facilities and Equipment | Parks and Recreation | $ 400,000 | $ 5,525 | 1.4% | ||||
| Sampson Playground Improvements | Public Facilities and Equipment | Parks and Recreation | $ 392,877 | $ - | 0% | ||||
| Citywide Parks & Parkways Improvements | Public Facilities and Equipment | Parks and Recreation | $ 378,751 | $ 378,751 | 100% | ||||
| General Meyer Complete Streets | Infrastructure | Streets and Rights of Way | $ 350,000 | $ - | 0% | ||||
| Resilient Algiers/Hung Dao Heritage Garden | Infrastructure | Stormwater Management | $ 340,800 | $ - | 0% | ||||
| Off - System Bridge Load Rating Services - Group 1 | Infrastructure | Streets and Rights of Way | $ 326,076 | $ 252,815 | 77.5% | ||||
| Norman Park Basketball Court Shelter Repair | Public Facilities and Equipment | Parks and Recreation | $ 300,000 | $ - | 0% | ||||
| Peoples Ave. linear park (Chef Hwy to Leon C. Simon) | Infrastructure | Streets and Rights of Way | $ 300,000 | $ - | 0% | ||||
| Pecan Grove Recreation Center | Public Facilities and Equipment | Parks and Recreation | $ 293,328 | $ 150,126 | 51.2% | ||||
| Breakwater Dr. (North Roadway - Dead End) | Infrastructure | Streets and Rights of Way | $ 292,377 | $ 292,377 | 100% | ||||
| District Attorney Office Renovations | Public Facilities and Equipment | Public Safety and Justice System | $ 292,107 | $ 277,502 | 95% | ||||
| Easton Playground Upgrades | Public Facilities and Equipment | Parks and Recreation | $ 274,301 | $ 274,301 | 100% | ||||
| Asset Management System (Infrastructure) | Infrastructure | Streets and Rights of Way | $ 265,100 | $ 265,100 | 100% | ||||
| Lafayette #1 Cemetery Improvements | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 261,206 | $ 261,206 | 100.0% | ||||
| McDonough/Harold Jene DeVore Playground | Public Facilities and Equipment | Parks and Recreation | $ 255,087 | $ 253,937 | 99.5% | ||||
| Mayo Bridge @ Morrison Canal | Infrastructure | Streets and Rights of Way | $ 250,000 | $ - | 0% | ||||
| Armstrong Park Lagoon Repairs | Public Facilities and Equipment | Parks and Recreation | $ 243,123 | $ 243,123 | 100% | ||||
| Virginia St (City Park - Clayton) - Conti St (City Park-Dead End) - Rosedale Dr (Virginia-Canal Blvd.) | Infrastructure | Streets and Rights of Way | $ 234,839 | $ 8,905 | 3.8% | ||||
| Washington Square Restoration Phase III | Public Facilities and Equipment | Parks and Recreation | $ 216,351 | $ 216,351 | 100% | ||||
| Algiers Point ADA Curb Ramps | Infrastructure | Streets and Rights of Way | $ 213,923 | $ 213,923 | 100% | ||||
| New Orleans East Incinerator Remediation | Public Facilities and Equipment | Public Safety and Justice System | $ 212,373 | $ 178,163 | 83.9% | ||||
| Elysian Fields Ave Walking Path Phase III | Public Facilities and Equipment | Parks and Recreation | $ 200,000 | $ - | 0% | ||||
| NOPD 4th District Police Station | Public Facilities and Equipment | Public Safety and Justice System | $ 192,214 | $ 192,214 | 100% | ||||
| Monticello Canal Culverts at Airline Highway | Infrastructure | Stormwater Management | $ 187,500 | $ - | 0% | ||||
| Oak Park Drainage Upgrades / Green Infrastructure | Infrastructure | Streets and Rights of Way | $ 184,455 | $ 64,848 | 35.2% | ||||
| New Orleans East Landbridge Restoration Increment I | Infrastructure | Streets and Rights of Way | $ 183,400 | $ 183,400 | 100% | ||||
| Gallier Hall Roof Restoration | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 168,904 | $ - | 0% | ||||
| Citywide Parks and Playground Improvements #3 (Peace Playground | Rome Playspot | Sampson Playground) | Public Facilities and Equipment | Parks and Recreation | $ 167,781 | $ 167,781 | 100% | ||||
| Richard Lee Playground Improvements | Public Facilities and Equipment | Parks and Recreation | $ 161,870 | $ 57,073 | 35.3% | ||||
| Homedale (Canal - West End), Center (33rd - Tacoma), Milne (Homedale - Florida), Walker (Marshal-Orl | Infrastructure | Streets and Rights of Way | $ 156,646 | $ 17,798 | 11.4% | ||||
| Old Gentilly Road Incinerator Bldg Site Demolitions | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 128,935 | $ 128,935 | 100% | ||||
| Citywide Energy Efficiency Upgrades 2021-2024 | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 124,278 | $ 124,278 | 100% | ||||
| City-Wide Payphone Removal Project Phase II | Infrastructure | Streets and Rights of Way | $ 123,250 | $ 123,250 | 100% | ||||
| Milneburg and Treme-Lafitte | Infrastructure | Streets and Rights of Way | $ 122,193 | $ - | 0% | ||||
| Dryades Kitchen Incubator Equipment | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 116,666 | $ - | 0% | ||||
| Genoa Road Drain Construction | Infrastructure | Streets and Rights of Way | $ 107,405 | $ 28,932 | 26.9% | ||||
| Independent Police Monitor - Police Misconduct Database | Public Facilities and Equipment | Public Safety and Justice System | $ 100,000 | $ 53,063 | 53.1% | ||||
| Hollygrove Greenline Trail (Joliet-Eagle) | Infrastructure | Streets and Rights of Way | $ 90,000 | $ - | 0% | ||||
| Milne Blvd (Mouton - Allen Toussaint) | Infrastructure | Streets and Rights of Way | $ 87,420 | $ 87,420 | 100% | ||||
| EMD Maintenance Facility | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 85,909 | $ 73,969 | 86.1% | ||||
| Lafayette #1 Cemetery Stormwater Improvements | Infrastructure | Stormwater Management | $ 82,894 | $ 8,410 | 10% | ||||
| NOFD 8th District Engines 33 & 40 Consolidated West Bank Fire Station | Public Facilities and Equipment | Public Safety and Justice System | $ 82,266 | $ 49,360 | 60% | ||||
| Odile Davis Park & Sampson Playground Improvements - Design Only | Public Facilities and Equipment | Parks and Recreation | $ 78,965 | $ 42,879 | 54.3% | ||||
| Carver-Penn Baseball Field Restoration & Rebuild | Public Facilities and Equipment | Parks and Recreation | $ 75,123 | $ - | 0% | ||||
| DPW Emergency Clean-up & Assessment Post Hurricane IDA | Infrastructure | Streets and Rights of Way | $ 65,930 | $ 65,930 | 100% | ||||
| NOPD - Miscellaneous Renovations (Windows, Parking Garage, Kennels) | Public Facilities and Equipment | Public Safety and Justice System | $ 57,147 | $ 31,427 | 55% | ||||
| ARPA: Traffic Signal Mast Arm Upgrades | Infrastructure | Streets and Rights of Way | $ 53,357 | $ 17,438 | 32.7% | ||||
| New Orleans Downtown Transit Center & Connecting Corridors | Public Facilities and Equipment | Public Facility Renovations and Equipment | $ 51,626 | $ - | 0% | ||||
| City Park Loop NOLA | Public Facilities and Equipment | Parks and Recreation | $ 50,000 | $ 50,000 | 100% | ||||
| Kerry Curley Park Basketball Court | Public Facilities and Equipment | Parks and Recreation | $ 50,000 | $ - | 0% | ||||
| Martin Luther King Blvd (St. Charles - S. Claiborne) | Infrastructure | Streets and Rights of Way | $ 47,298 | $ 45,016 | 95.2% | ||||
| Cut-Off Splash Pad and Wilderness Park Improvements | Public Facilities and Equipment | Parks and Recreation | $ 44,629 | $ 32,567 | 73% | ||||
| George Washington Carver Playground (Zone A - all Field Improve) | Public Facilities and Equipment | Parks and Recreation | $ 38,066 | $ 11,077 | 29.1% | ||||
| Coliseum Square Improvements & Central City Neutral Ground Beautification | Public Facilities and Equipment | Parks and Recreation | $ 36,307 | $ 13,100 | 36.1% | ||||
| Hunter's Field Restroom Repairs | Public Facilities and Equipment | Parks and Recreation | $ 33,545 | $ 33,545 | 100% | ||||
| East Carrollton Group B and C (RR033/RR034) | Infrastructure | Streets and Rights of Way | $ 33,000 | $ 29,735 | 90.1% | ||||
| Milneburg Neighborhood Stormwater Resilience | Infrastructure | Stormwater Management | $ 30,644 | $ 30,644 | 100% | ||||
| Alma Peters Playspot Play Equipment | Public Facilities and Equipment | Parks and Recreation | $ 18,282 | $ 18,282 | 100% | ||||
| Pratt Playground Canopy Installation | Public Facilities and Equipment | Parks and Recreation | $ 16,508 | $ 16,508 | 100% | ||||
| Coliseum Square Trash Receptacles | Public Facilities and Equipment | Parks and Recreation | $ 11,000 | $ 11,000 | 100% | ||||
| West Bank Soccer Complex (Brechtel Park) - Clubhouse Demolition | Public Facilities and Equipment | Parks and Recreation | $ 8,000 | $ 8,000 | 100% | ||||
| I-510 & Dwyer Rd. Cameras (Illegal Tire Dumping) - Public Safety | Public Facilities and Equipment | Public Safety and Justice System | $ 7,324 | $ 7,324 | 100% | ||||
| Street Lights, Signs and Traffic Signals (Parks and Recreation) | Public Facilities and Equipment | Parks and Recreation | $ 6,446 | $ 6,446 | 100% | ||||
| S. Dupre (Canal - Tulane) and Gayoso (Canal - Banks) | Infrastructure | Streets and Rights of Way | $ 5,645 | $ - | 0% | ||||
| I-510 & Dwyer Rd. Cameras (Illegal Tire Dumping) - Streets | Infrastructure | Streets and Rights of Way | $ 1,325 | $ 1,325 | 100% | ||||
| St. Charles Ave (Louisiana-Nashville) | Infrastructure | Streets and Rights of Way | $ 208 | $ 208 | 100% |