Sewerage & Water Board of New Orleans
FY 2000-2004 Capital Program
Power Projects Detail (in thousands)
|
This table shows how costs for maintaining the S&WB power plant are apportioned to each system. |
|||||||
|
TOTAL |
|||||||
|
FIVE-YEAR |
|||||||
|
Capital Program # and Description |
W/S/D%(k) |
2000 |
2001 |
2002 |
2003 |
2004 |
PROGRAM |
|
POWER PROJECTS |
|||||||
|
601 Earhart Blvd. Corridor |
.20/00/.80 |
$ 0 |
$ 300 |
$ 300 |
$ 0 |
$ 0 |
$ 600 |
|
603 60Hz Gen for Algiers Purification Plant |
100/00/00 |
50 |
0 |
0 |
0 |
0 |
50 |
|
605 Provide Emergency Power at Central Yard |
.45/.45/.10 |
50 |
725 |
0 |
0 |
0 |
775 |
|
609 Extensions & Replacements - Radio Comm System(d) |
.13/.34/.53 |
50 |
50 |
50 |
50 |
50 |
250 |
|
610 Underground Power Feeders |
00/00/100 |
600 |
2,000 |
1,000 |
1,500 |
1,500 |
6,600 |
|
611 Monit Rainfall & Drainage Operations |
00/00/100 |
150 |
0 |
0 |
0 |
0 |
150 |
|
612 Furn Generators for Drainage Facilities |
00/00/100 |
500 |
7,500 |
3,500 |
2,750 |
0 |
14,250 |
|
613 Modification of Steam System |
.20/.05/.75 |
900 |
1,200 |
0 |
0 |
0 |
2,100 |
|
624 Extension & Replacements to Electrical System (d) |
.20/.05/.75 |
600 |
300 |
300 |
300 |
300 |
1,800 |
|
682 60 Hz Generation |
.20/.05/.75 |
1,200 |
15,650 |
7,350 |
250 |
400 |
24,850 |
|
695 Monitoring & Supervision Control for SPS |
00/100/00 |
50 |
50 |
50 |
50 |
50 |
250 |
|
696 Switchgear & Motor Control-DPS #12 |
00/00/100 |
50 |
0 |
0 |
0 |
0 |
50 |
|
TOTAL POWER PROJECTS |
$ 4,200 |
$ 27,775 |
$ 12,550 |
$ 4,900 |
$ 2,300 |
$ 51,725 |
|
|
(d) Replacement Capital |
|||||||
|
(k) Percentage cost for Water/Sewerage/Drainage |
|||||||
|
SPS - Sewage Pump Station |
|||||||
|
DPS - Drainage Pump Station |
|||||||
Source: S&WB 2000 5-Year Capital Program
Recompiled by BGR, July 2000