Bureau of Governmental Research


[Small Home Icon]

[Small BGR Logo]

[Small Publications Icon]

[Small Links Icon]

[Small Membership Icon]

[Small Contact Us Icon]

Home

About
BGR

Publications

Research
Links

Membership
Information

Contact
Us

Local
Budgets

Overview and Status Report on the
New Orleans Capital Program

CONTENTS

Capital Planning and Budgeting in New Orleans

Capital Funding Sources

1995-Approved Bonds
Current Capital  Budget
Capital Interest Underwrites Operating Budget
Debt Service
Bond Rating
Future Capital Improvements
Conclusion

The City of New Orleans’ capital improvement initiative approved by voters in 1995 is approaching an end. At the current rate, construction activities authorized in 1995 will probably wind down by 2003. The City has proposed another bond proposition, which will be presented to the voters on November 7, 2000.

BGR’s November 1997 Status Report on 1995 City Capital Program analyzed the City’s progress in carrying out the 1995 ballot proposition (see Publications at www.bgr.org). This report updates BGR’s earlier analysis. It also examines trends in the City’s debt, and the status of coordinated capital planning among the City and other governmental entities in Orleans Parish.

Capital Planning and Budgeting in New Orleans

The capital planning process follows an annual cycle. Each spring, city departments, subordinate entities, and parochial offices occupying City facilities (e.g., the judicial system) submit five-year capital project requests. The City Planning Commission staff prioritizes the requests by scoring them on a 0 to 3 point scale for each of 17 weighted criteria designed to compare the relative importance of each project. The criteria (and the weights applied to the scores) are shown in Table 1.

TABLE 1
CAPITAL PROJECT SCORING CRITERIA
Criteria  Scoring Weight
Public Health and Safety  3
External Requirements 3
Protection of Capital Stock 3
Economic Development 3
Operating Budget Impact 3
Life Expectancy of Project 3
Percentage of Population Served by Project 2
Relation to Adopted Plans  2
Intensity of Use  2
Scheduling 2
Benefit/Cost 2
Potential for Duplication 2
Availability of Financing  1
Special Need 1
Energy Consumption 1
Timelines/External 1
Public Support 1

Based on projections of available funds, the City Planning Commission recommends a five-year capital program of prioritized projects to the Mayor by October 15th of each year. The City charter requires the Mayor to submit the program and his recommendations to the City Council by November 1st. Once the five-year program is approved, the first year of the capital program becomes the City’s capital budget appropriation for that year. As the budget year progresses, the City Council often appropriates funds for additional projects, typically because state or federal grants become available.

The City’s capital planning process is a “bottom up” approach; it evaluates separate projects independently submitted by City departments and agencies. Theoretically, the City’s master plan should provide a broader, long-range perspective. However, the existing 1980 master plan is outdated, and has been largely irrelevant to the capital planning process. The City Planning Commission is currently working on a major initiative to develop a new master plan. The capital planning process has little bearing on the most costly component of the City’s capital spending: street projects. Minor street projects bypass the planning process entirely. For major streets the planning commission sometimes suggests changes to the program proposed by the Department of Public Works. (For example, in the new 2001 – 2005 program, the planning commission is recommending a new $900,000 annual line item for emergency street projects.) But the streets are not prioritized against other projects, and the planning commission defers to the judgement of the Department of Public Works on project selection.

In 1995, the planning commission’s proposed capital program included a list of recommended major street projects. However, since 1995, none of the City’s capital budgets have listed any street by name, with the exception of three streets in the New Orleans Business and Industrial District (NOBID). Instead, the adopted capital budgets simply appropriate large lump sums for major and minor streets, leaving individual streets to be selected outside of the formal planning and budget process.

Much like street projects, airport projects are not prioritized against other projects. However, the planning commission staff reviews airport projects for compliance with the airport’s proposed master plan. Unlike street projects, the airport’s capital projects are individually listed in the capital budget.

The City’s planning process does not cover the activities of independent boards and commissions that lie outside of the city charter’s control. Examples include the Sewerage and Water Board, the Regional Transit Authority, and the Orleans Levee District. The non-applicability of the process to the Sewerage and Water Board is particularly significant. That agency is responsible for sewer, water, and drainage facilities beneath the streets, which necessitates close coordination to avoid the City and the board tearing up each other’s work.

Before the planning process even starts, all but a fraction of available capital funding is already earmarked for specific categories such as streets, public buildings, and airports. These categories are established by the terms of bond propositions or by the nature of the funding source (as is the case for airport projects). With so little flexibility, the planning process has minimal impact on how money is allocated among different categories of capital improvements. What the process does accomplish is to filter and prioritize non-street, non-airport projects within the predetermined funding categories.

Capital Funding Sources

Funding for capital projects comes from a variety of sources:

1995-Approved Bonds

In 1995, the voters approved a two-part capital financing package: $147.4 million in GO bonds, and $15.8 million in ten-year tax limited bonds backed by a 2.5 mill property tax previously earmarked for neighborhood housing and economic development. A third component of the 1995 program did not require voter approval: $8.8 million of borrowing backed by a $1.25 million annual portion of the land based casino’s payments. The casino’s bankruptcy derailed this component, which remains unfunded, despite the casino’s eventual emergence from bankruptcy.

The GO bond portion of the 1995 referendum authorized five discrete categories of projects. See Table 2.

TABLE 2
GENERAL OBLIGATION BOND IMPROVEMENTS
(APPROVED IN 1995)

Major streets

$ 41,200,000

Minor streets

50,000,000

Parks, playgrounds, and recreational facilities.

2,330,000

Public buildings and facilities (includes $12 million for the convention center and $5 million for NOBID infrastructure improvements.)

47,910,000

Improvements to the Criminal Court Building, Central Lockup, and the Municipal Traffic Court Building.

5,960,000

TOTAL GENERAL OBLIGATION BONDS

$147,400,000

Source: Text of July 15, 1995 Ballot Proposition No. 1.

The 1995 referendum dedicated the $15.8 million funding component to parks and recreation facilities, and equipment for fire fighting, sanitation, and mosquito control. The ballot proposition did not specify how the $15.8 million was to be distributed among these categories; however, the City’s capital program divided the funds as shown in Table 3.

TABLE 3
LIMITED TAX BOND IMPROVEMENTS
APPROVED IN 1995

New Orleans Recreation Department

$ 10,350,000

Parks and Parkway Commission (Lawrence Square)

800,000

Audubon Park Improvements

500,000

City Park Project Greenspace

245,000

Equipment

Fire Apparatus

3,150,000

Sanitation Heavy Equipment

500,000

Mosquito Control Equipment

255,000

TOTAL LIMITED TAX BONDS

$ 15,800,000

Source: Official Statement, $15,800,000 Limited Tax Bonds, Series 1996, Appendix F.

The City issued the bonds authorized by the 1995 propositions in five increments; the final $32.4 million increment was sold in November 1999. See Table 4.

Where did all of the 1995 bond money go? For about half of the money, the answer is nowhere. At the end of August 2000, $76.9 of the $163.2 million from the bonds had not been spent or encumbered. See Table 4. Although all of this had been appropriated by 1999 (i.e., authorized by the City Council for expenditure), many projects have not progressed enough to lock in the funds under a contractual obligation or purchase order. Funds are not considered encumbered until they are obligated in one of these ways.

One reason for the sluggish schedule performance is that the City had an enormous backlog of capital work in progress in 1995 when the most recent bonds were approved. At the beginning of 1995, the City had about $62.8 million of unencumbered pre-1995 bonds designated for its backlog of capital projects.

Another reason much money remains unencumbered is that street projects have been moving at a snail’s pace. Of the $76.9 million in unencumbered 1995 bond program money, about $60 million is for street projects. The City has a much better track record implementing non-street projects. On a dollar-value basis, 74% of the 1995 program’s funding for non-street projects was expended or encumbered, compared to only 38% for street projects, as of August 2000.

These differences mirror a division of responsibility for capital projects. Non-street projects are administered by the Capital Projects Division of the Chief Administrative Office. Street projects are administered separately by the Department of Public Works. Both organizations ultimately report to the Chief Administrative Officer.

Non-Street Projects

The vast majority of the non-street projects funded by the 1995-approved bonds are either complete or under construction. Table 5 summarizes this status, as reported by the City.

 Table 5 
NON-STREET PROJECTS STATUS 
(October 2000)

Budget Years

Project

Bond Funds

Status
(October 2000)

1996

Fire Apparatus Replacement

$ 3,150,000

Completed

1996

Crime Lab Addition

415,000

Completed

1996

Criminal Courts Reroofing

275,000

Completed

1996

Civil Courts Cooling Tower Replacement

200,000

Completed

1996

Stallings Center Improvements

550,000

Completed

1996

City-wide Lighting Improvements, NORD

500,000

Completed

1996

Comiskey Playground Improvements

300,000

Completed

1996-97

City Hall HVAC Improvements, Ph. I & II

1,500,000

Completed

1996

City Hall Fire Alarm Upgrades

600,000

Completed

1996-97

City Hall Sprinkler System

1,000,000

Completed

1996

Golden Age Center Improvements.

550,000

Completed

1996-97

City-wide NORD Roofing & Painting

300,000

Completed

1996

Conrad Playground Improvements

150,000

Completed

1996

Mugrauer Center Improvements

300,000

Completed

1996

Harrell Stadium Improvements

550,000

Completed

1996

Harrell Pool Improvements

700,000

Completed

1996

Joe Brown Pool

250,000

Completed

1996

Taylor Pool

800,000

Completed

1996

Fischer Playground Improvements

500,000

Completed

1996

Pradat Pool

800,000

Completed

1996

Cabrini Playground Improvements

180,000

Completed

1996

Treme Center & Pool Improvements

574,200

Completed

1996

Pontchartrain Park NORD Facility

100,000

Completed

1996

A.L. Davis Playground Improvements

303,000

Completed

1996

Willow Brook Playground Improvements

200,000

Completed

1996

Behrman Stadium Improvements

145,000

Completed

1996

Sanitation Equipment Acquisition

500,000

Completed

1996

Mosquito Control Equip. Acquisition

255,000

Completed

1996

Laurence Square Renovations

800,000

Completed

1996-97

City Park Project Greenspace, Ph. I & II

750,000

Completed

1996-97

Audubon Park Improvements, Ph. I & II

1,000,000

Completed

1996-97

Central Library Improvements

475,000

Completed

1996

334 Royal (VCC) Improvements

335,000

Completed

1996-98

Fuel System Compliance Program, Ph. I, II, & III

1,750,000

Completed

1996-97

Convention Center Expansion

12,000,000

Completed

1996

NOMA Street Lighting

220,000

Completed

1996

Citywide Play Equipment, Ph. I

450,000

Construction

1996

Lemann Pool Improvements

827,800

Construction

1996

Milne Pool (design and match for state funds)

900,000

Working Drawings

1996

Mandeville Center Improvements (NORD)

520,000

Design

1997

Fire Stations #26 & #36 Improvements

685,000

Completed

1997

Police Admin. Bldg. Improvements., Ph. II

730,000

Completed

1997

ADA Building Improvements, Ph. I

150,000

Completed

1997-98

House of Detention Sprinkler Sys., Ph. I & II

1,100,000

Completed

1997

House of Detention Re-roofing

385,000

Completed

1997-98

Mechanical Upgrades - City Buildings

250,000

Completed

1997-98

Electrical Upgrades - City Buildings

250,000

Completed

1997-98

Plumbing Upgrades - City Buildings

250,000

Completed

1997

City-wide NORD Fencing

100,000

Completed

1997

Main Brake Tag Station Improvements.

1,000,000

Completed

1997

Re-roof Mosq. Control Operations Bldg.

125,000

Completed

1997

Smith Library

150,000

Completed

1997

Alvar Library Improvements

100,000

Completed

1997

Municipal/Traffic Ct. Sprinkler Sys.

850,000

Construction

1997-99

Gentilly Landfill Closure

5,650,000

Construction

1997

Burke Park Renovations

600,000

Construction

1997

Police Communication Center Upgrades

850,000

Construction

1997

City-wide Play Equipment, Ph. II

100,000

Bidding

1997

Municipal/Traffic Court Elevator Improvements.

75,000

Working Drawings

1997

Criminal Courts HVAC Upgrades

925,000

Working Drawings

1997

Youth Study Center Renov. & Expan.

2,200,000

Bidding

1997-98

Gentilly Library Improvements

400,000

Bidding

1998

Fire Station #6 & Supply Shop Improvements

370,000

Completed

1998

City-wide NORD Fencing

100,000

Construction

1998

Police Admin. Bldg. Improv., Ph. III

1,500,000

Construction

1998

MTA East Shower Facility

150,000

Construction

1998

Central Library Basement Waterproofing

225,000

Construction

1998

N.O. East Regional Library Improvements.

175,000

Construction

1998-99

Local Match for State-funded New Orleans Regional Medical Center (NORMC) Projects

1,000,000

Design

1998-99

ADA Building Improvements

250,000

Construction

1998

Land Acquisition and Design, New District Fire Station (near Third & Broad)

370,000

Land Acquisition Underway

1998

Relocate Parking Adjudication to MTA

275,000

Completed

1999

House of Detention Elevator Repairs

750,000

Completed

1999

Gallier Hall Fire Alarm Improvements

330,000

Design

1999

House of Detention HVAC Improvements.

1,100,000

Design

1999

DA's Office Mechanical Sys. Improvements.

250,000

Design

1999

Criminal Cts. Fire Alarm Sys. Upgrades

500,000

Design

1999

Earhart Blvd. Lighting

175,000

Design

1999

Coliseum Square Improvements

325,000

Design

1999

Mosquito Control Admin. Bldg. Renov.

235,000

Working Drawings

1999

Trailways Bldg. Demolition

400,000

Design

1999

Broad Street Fuel Facility Canopies

125,000

Design

1999

MTA Fire Training Facility, Ph. V

675,000

Working Drawings

1999

Edna Pillsbury Health Clinic Improvements.

2,875,000

Design

1999

Design - New District Station (Area of Third & Broad)

1,800,000

Awaiting land acquisition

1998

Available for Reprogramming

175,000

 

1999

Available for Reprogramming

250,000

 

Total, Non-Street Projects

$ 67,000,000

Source: 1996 City of New Orleans Capital Budget, as updated by Chief Administrative Office

Street Projects

Sixty-two percent of the capital funding approved by the voters in 1995 was specifically designated for major ($41.2 million) and minor streets ($50.0 million). Table 6 summarizes the status of street projects funded by the program, as reported by the City. The ballot proposition listed a number of major streets by name. The City subsequently programmed several others for funding as well, and earmarked an additional $5 million for NOBID streets. (1) The 1995 bond proposition included $50 million for “minor streets” simply as a lump sum category without naming specific streets.

 Table 6 
STREET PROJECTS STATUS 
(October 2000)

Project

Bond Funds

Status

     

Major Streets Listed in the 1995 Bond Proposition

   

Alcee Fortier (Chef to Dwyer); Pressburg (Read to Wright)

$ 3,377,730

Completed

Almonaster (Franklin to Law)

2,548,230

Under Construction

Crowder (I-10 to Morrison)

0

Resurfaced using other funds

Esplanade (Rampart to Claiborne); N. Galvez (Esplanade to Elysian Fields)

4,820,640

Completed

Jefferson (St. Charles to Claiborne)

443,821

Under Construction

Louisa (Almonaster to Higgins)

0

Deferred

Louisiana (Tchoupitoulas to Magazine)

89,940

Partially designed; now deferred

Magazine (Broadway to Napoleon); Prytania (Jefferson to Napoleon)

4,546,172

Design (preliminary)

Martin Luther King (Claiborne to Broad)

822,090

Design (final)

McArthur (Gen. DeGaulle to Kabel)

2,907,410

Completed

N. Galvez (Clouet to Poland); Chartres; Elysian Fields

3,280,637

Design (final)

Oak (Leake to Carrollton)

751,627

Design (preliminary)

Poydras (Claiborne to Broad)

404,910

Design (final)

Teche (Bringier to Opelousas) and Newton

3,817,720

Design (final)

     

Major Streets Added by the City

   

Fountainbleau (Carrollton to Broadway); Octavia (Fountainbleau to Grape)

2,551,027

Completed

Morrison Rd. (Jahncke Canal to Vincent St.)

2,348,796

Bids Received

Tchoupitoulas St. (Clarence Henry to Felicity)

8,489,250

Completed

     

Minor Street Projects

   

Abundance (Dead End to Annette);Lafreniere (Allen to Annette)

322,478

Design (preliminary)

Andry, Piety, Etc

1,337,278

Design (preliminary)

Argonne (Polk to Harrison)

2,194,854

Design (final)

Baronne (Napoleon to Delachaise); First (S. Roman to N. Claiborne)

1,468,136

Design (preliminary)

Burthe (Fern to Broadway)

1,661,068

Bids Received

Camelot (Chef Menteur to Dwyer Canal)

1,561,548

Design (preliminary)

Carondelet; Chestnut

1,308,811

Design (final)

Carondelet (Napoleon to Louisiana)

1,523,146

Design (final)

Cernay, Dreux, Forstall, Knight

2,205,000

Completed

Charlton (Pratt to Paris); Chatham (Pratt to Filmore)

1,134,879

Design (preliminary)

Chatham (Filmore to Robert E. Lee)

1,324,396

Design (preliminary)

Clematis (Gentilly to Humanity)

1,569,880

Design (preliminary)

Clouet (N. Robertson to N. Miro)

1,545,053

Completed

Elenore and Perrier

1,330,546

Design (final)

Emerald (Opal to Zicon); Walker (Canal to Marshall Foch); Center (Tacoma to 36th)

1,288,746

Design (preliminary)

Erickson, Finland, Hyman, Rhodes

2,466,298

Design (preliminary)

Erie (Hendee to Whitney); Evergreen (Dead End to Bringier); Comet( Fiesta to Prancer)

1,132,211

Design (preliminary)

Fairfax (Westchester to Sullen); Herald (Gen. De Gaulle to Berkeley); Essex (Fairfax to Sullen)

1,489,711

Design (preliminary)

Forstall (Claiborne to Rocheblave)

1,229,508

Design (preliminary)

Gallier (N. Robertson to N. Miro)

2,035,000

Design (final)

Germain (Vicksburg to Orleans); S. Alexander (D'Hemecourt to Cleveland)

1,226,541

Design (preliminary)

Hampson (Fern to Broadway)

1,935,706

Bids Received

Hudson Place, Eton

2,850,000

Completed

Madrid, Soldiers, Mendez

1,099,546

Design (preliminary)

N. Dorgenois (Bern to Elysian Fields)

1,869,546

Design (preliminary)

N. Olympia (St. Louis to Orleans)

260,610

Design (preliminary)

Peniston (Carondelet to Freret)

900,307

Design (preliminary)

Piety (St. Claude to Urquhart); Congress (St. Claude to N. Robertson)

791,583

Design (preliminary)

Prieur (Upperline to Napoleon)

340,171

Design (preliminary)

River Oaks (Gen. De Gaulle Berkeley)

302,318

Design (preliminary)

Royal (Caffin to Charbonnet)

201,712

Design (preliminary)

S. Gayoso (Fontainebleau to Washington); Upperline ( Johnson to Tonti)

1,185,868

Design (preliminary)

Touro (Claiborne to St. Claude)

1,132,546

Design (final)

Walmsley, Willow, Valmont, Vendome

4,545,000

Design (final)

Wales, Prentiss, Reineer, Selma

1,229,999

Design (preliminary)

     

NOBID Projects

   

Industrial Parkway

1,097,664

Completed

Intracoastal Drive

747,336

Completed

Michoud Blvd

3,155,000

Completed

TOTAL 1995 BOND PROGRAM STREET FUNDING

$96,200,000

The City’s plans have changed for several major street projects since 1995:

Street surface work (the City’s responsibility) is highly dependent on subsurface work involving water, sewer, and drainage lines (largely the Sewerage and Water Board’s responsibility). Both entities overtly recognize the need to work together. The two entities have a written agreement that establishes a system for planning, designing, and executing subsurface work — at least in theory. In practice, the system is non-existent when it comes to project selection. For project implementation, the system has been slow, cumbersome, and sometimes ineffective.

For example, the Sewerage and Water Board was planning an underground canal on Jefferson Avenue that would have destroyed much of the reconstruction work that the City was simultaneously planning before the 1995 bond referendum. The City went so far as to pay for a final design, but eventually abandoned the plan in favor of a less expensive overlay.

Part of the problem was the uncertainty of when the canal would be built. The board’s capital program lists the canal project in 2001-2002, but construction is unlikely before 2004, and could be later, depending on approval by the Corps of Engineers. The result: money spent on a street design that will never be built and on an overlay that will probably be torn up few years after it is completed. 

While coordination between the City and the Sewerage and Water Board on street projects has been poor, it is improving. The Mayor recently formed the Public Works Coordinating Council — an inter-agency task force to address the coordination and schedule problems. BGR interviewed a number of participants in the process, and their general consensus is that the task force has prompted action on some of the languishing street projects, at least in the short-term.

Banking on the performance improvements it hopes to achieve, the City has laid out an aggressive schedule to have all street projects under construction by April of 2001. This would require awarding street construction contracts eight times faster than the City’s historical performance since 1995.

There is no question that the street program can be accelerated. However, an eight-fold improvement in such a short period is unlikely. Further, it runs the risk of sacrificing engineering design quality and overloading the capacity of the local construction industry to handle the work economically. (Only a small number of contractors are capable of handling the City’s street work.)

The City will not complete all of the street work it contemplated in 1995. In the first place, the City had to eliminate some projects because $8.8 million of the capital program secured by the casino revenue did not materialize. The City had planned to devote this entire amount to street projects. Also, the Chief Administrative Office indicates that in the early stages of the 1995 program, construction bids ran high, an effect attributed to the strong economy and a bidders market for street work. An alternative explanation is that the City bid the initial batch of bond program street projects over too short an interval, and drove up construction prices.

Accountability for the minor street projects remains a BGR concern. The minor street projects do not go through the City’s capital planning process. Thus, the largest single component of the 1995 bond authorization — an undifferentiated $50 million pool of funds — bypassed the system designed to insure that capital funding is spent on the City’s highest priorities. The choice of minor street projects was relegated to a fundamentally political process.

City officials downplay this issue, contending that all of the street projects funded are worthwhile, and would probably receive a high priority in a formal ranking process.

In 1995, BGR recommended that the City prioritize minor streets based on the physical condition of each street. In principle, the City established such a system utilizing American Public Works Association criteria. Nonetheless, minor street funding was divided equally among the five council districts; each council member determined priorities within the district.

Council members were furnished the physical condition ratings to make their choices, and the Chief Administrative Officer indicates that all of the streets chosen were in the bottom three (of seven) condition categories (poor, very poor, and failed). BGR spot-checked eight minor street projects in one council district, and found that this was true in each instance. Other than the council member's personal preference, BGR was unable to determine a rationale for why eight streets were chosen over the other 208 streets in that district.

Current Capital Budget

The adopted 2000 capital budget authorizes $46.4 million in projects. See Table 7. About 97% of this is for the airport; the remaining 3% ($1.4 million) is for minor streets and a smattering of smaller projects. The City has no direct control over this imbalance. Capital improvements at the airport are supported by federal money earmarked for airport purposes, and by local revenues generated from the airport’s operation; these funds are generally restricted to airport-related projects.

TABLE 7
CITY OF NEW ORLEANS 2000 CAPITAL BUDGET

Miscellaneous Capital Funds

Citywide Playground Equipment

$ 50,000

NORD Playspot Repairs

75,000

Recovery I Monitoring (Sanitation Department)

25,000

Nursery Administration Building Roof Replacement

25,000

City Park Improvement Assoc., Outdoor Track Lighting

25,000

Public Library Emergency Branch Repairs

50,000

Mosquito Control Board Termite Control Program

25,000

CAO’s Capital Projects Planning Fund

100,000

Juvenile Court Access Control & Security

25,000

Subtotal Miscellaneous Capital Funds

$ 400,000

Community Development Funds

Minor Street Improvements

$ 1,000,000

Airport Funds (discretionary, bond, and federal funds combined)

Program Management

$ 4,085,310

Landscaping Stage 3 (Phase 2-5)

1,500,000

Apron Drainage, Oil/Water Separator Ph. 2

5,045,500

Airport Access Road Improvements

3,905,000

Overflow Parking Lot/West Taxi Lot Lounge

3,400,000

Aberdeen Street Extension

3,000,000

Concessions Improvement Program

3,000,000

Committed Airport Planning Studies

4,000,000

Parking Garage Elevators

1,000,000

Program Management Office Build Out

400,000

Continental Airlines President’s Club

750,000

Roadway Meetings

300,000

TACA Building Interior Renovations

500,000

Upgrade Garage Equipment

1,800,000

Upgrade Loading Bridges

1,000,000

Large Equipment Purchases

1,000,000

NOAB Staff Relocation to West Terminal

500,000

New Restroom Facilities for Concourse B

1,000,000

Perishable Goods Center Federal Inspection Facility

300,000

Residential Sound Insulation Ph. 1

1,500,000

EAC Facility Building #2

7,000,000

Subtotal Airport Funds

$ 44,985,810

___________

TOTAL 2000 CAPITAL BUDGET

$ 46,385,810

Source: Ordinance No. 19474, adopted December 1999; and BGR summary calculations. Does not reflect subsequent amendments, which are not significant.

Because the last of the funds authorized by the voters in 1995 had been appropriated in the 1999 capital budget, only minimal funding for non-airport projects was available for 2000.

A limited untapped pool of capital funding remains in the Capital Improvements and Infrastructure Trust Fund established by the 1995 bond election. The 2.5 mill tax dedicated to that fund exceeds debt service on the $15.8 million bond issue supported by it. The fund’s balance stood at $5.7 in 1999, and should reach $7.7 million by the end of 2000.

Capital Interest Underwrites Operating Budget

The City’s operating budget is partially supported by interest earned on unspent capital funds. See Table 8.

TABLE 8
OPERATING BUDGET REVENUE FROM
INTEREST ON CAPITAL FUNDS

1996

 

$ 4,500,000

1997

 

7,300,000

1998

 

8,400,000

1999

 

8,200,000

2000

 

4,800,000

Source: City of New Orleans Comprehensive Annual Financial Reports, 1996 – 1999, Note 10. Interest for 2000 is from the City’s adopted operating budget.

The New Orleans City Charter (§ 6-204) defines capital project funds to include “monies derived … from the proceeds of bonds.” The City’s longstanding practice is to construe “proceeds” to mean only the immediate proceeds from sale of bonds, not the subsequent interest earned on those proceeds. Another section of the charter, §6-201(2)(a), requires all receipts to be deposited in the City’s general fund, unless otherwise mandated by law. Under this latter provision, interest earned on unspent bond proceeds goes to the general fund, where it is kept to subsidize the City’s operating budget.

Diverting interest to the operating budget departs from the more widely accepted municipal management practice of crediting interest income to the capital fund that produces it. The City’s approach effectively shrinks the funding originally approved by the voters for capital projects. Over time, inflation erodes the purchasing power of the bond proceeds. Interest income could attenuate this effect, but the erosion continues unabated in New Orleans when interest goes to the operating budget. A second undesirable effect of this practice is that the City’s annual operating budget becomes dependent on non-recurring, long-term debt financing.

Debt Service

Annual debt service on the City’s several forms of long-term debt will peak in 2002 at approximately $64.6 million, and will drop through 2012 when it levels off at about $46.5 million until 2021. (2) See Figure A. This debt service does not include new borrowing authorized by the City Council shortly before this report went to press. The City plans to issue an additional $27 million in certificates of indebtedness to pay lawsuit judgments, and an additional $180 million in bonds to finance one of the City’s retirement systems.

Figure A
PROJECTED ANNUAL CITY DEBT SERVICE

Source: City of New Orleans Comprehensive Financial Report, 1999 and payment schedules for the City’s outstanding certificates of indebtedness.

In 1995, a 10.6 mill tax increase staged over three years was projected to retire the proposed general obligation bonds. Because assessed property values grew significantly, and because a large portion of the City’s debt was refinanced in 1995, the increase was not necessary. The City’s debt service millage has remained at 26.9 mills since 1992.

Recent growth in assessed values provide an unencumbered revenue stream to support additional GO borrowing under current millage rates. City officials are banking on this excess to issue the new bonds proposed on the November 7, 2000 ballot without a tax increase.

Bond Rating

Rating companies give the City good marks for financial management. Nevertheless, New Orleans’ high poverty rate and its penchant for covering budget shortfalls with non-recurring revenue drag down the City’s bond rating. The most recent Moody’s Investors Service rating (August 1999) classified the City’s GO bonds as “Baa2.” This is unchanged from the May 1998 rating, and puts New Orleans in the lowest 10% of bond ratings among the nation’s largest cities. (3) To avoid paying higher interest because of its weak bond rating, the City’s recent general obligation bond offerings have included repayment insurance that pushes the ratings for the insured bonds to a top notch “Aaa” level. The improved bond rating comes at a cost: the City pays higher interest rates to cover the price of the insurance premium.

The insurance protects the bondholders, not the City. The insurance pays the bondholders if the City defaults. The bondholders would be paid by the insurance company, which would then collect from the City under the City’s “full faith and credit” obligation.

Future Capital Improvements

The City’s 2001 capital budgeting process is now well underway. Capital funding requests in this year’s cycle total approximately $730.5 million over the next five years. On August 3, 2000, the City Council approved a $150 million bond proposition for the November 7 ballot that would fund the City’s capital program for this five-year period. Additionally, the Law Enforcement District of Orleans Parish (in effect, the Orleans Parish Criminal Sheriff) has proposed another $27 million in bonds for the same ballot. These bond issues will not come close to funding the capital requests submitted during the current budget process.

The demand for capital projects far outstrips available funding. Further, the requests identified through the City’s formal capital programming process constitute only part of the larger pool of capital requirements in local government. Other independent entities in Orleans Parish have major capital improvement plans: most notably, the Orleans Parish Schools, the Sewerage and Water Board, and the Regional Transit Authority. When combined with the City’s, capital funding requests of local entities for identifiable projects are in the $3 billion range. Even discounting “wish list” projects, this level of demand is staggering — particularly in view of the existing debt load of local entities in Orleans Parish.

Long-term direct municipal debt for the City of New Orleans was $599.4 million at the end of 1999. This consisted of general obligation bonds, limited tax bonds, and other forms of long-term borrowing, but only for the City government itself. This direct City debt is only 38% of local government debt. Including the various forms of overlapping debt of other entities (the Sewerage and Water Board, the Orleans Parish Schools, the Orleans Levee District, the Regional Transit Authority, the Audubon Commission, the Law Enforcement District, and the Aviation Board, etc.), the combined long-term debt of local governments in Orleans Parish stood at about $1.56 billion at the end of 1999. (4) On a per capita basis, this comes to $3,386, which is well over the national average of $2,952. (5) While local government’s per capita debt has been growing as a mathematical consequence of Orleans Parish loosing population, the debt load would still exceed the national average if the 1990 population were used. (6)

How is it that local government debt is so high while the overall quality of its facilities and infrastructure remains so low? BGR suggests three reasons:

The combined effect of these factors is starkly demonstrated by the City’s situation: it implements about $25 to $30 million per year in capital improvements, but spends about $50 million annually to retire the long-term debt that funded for those improvements. (7)

In view of the City’s level of debt, should the City stop borrowing to finance capital improvements? At present, the City has no other alternative. The City’s infrastructure is badly in need of work. State law seriously constrains the City’s ability to raise revenue. Freeing up money for capital improvements through savings in the City’s operating budget is a theoretical possibility, but not practically achievable in the near term.

Although different funding mechanisms support various components local government debt (e.g., property taxes, user fees, service charges), the entities responsible for this debt all ultimately answer to the same citizens of Orleans Parish. Yet there is no system by which capital needs of different governmental units in the parish are collectively prioritized and coordinated. Are roads more important than schools? Is drainage more important than recreation? These essential questions are not addressed in any capital planning process.

Conclusion

The City’s record under the capital improvement program approved by the voters in 1995 has been mixed. 

For non-street projects, the City has generally met its original commitments, with most of the non-street program complete, and the balance well underway. The situation is starkly different for street projects. Planning for the street projects is a serious weakness. Implementation has been slow, and coordination with other agencies has been lacking. Most of the street projects remain incomplete. The significant backlog of street projects at the start of the 1995 program explains part of this track record, but the backlog of projects today is actually greater than it was in 1995.

The City is well aware of the problem, and recently initiated a number of project management improvements to address it. Participants in the effort are optimistic that the improvements will bear fruit. 

A key factor in BGR’s support of the City’s 1995 bond issue was the City’s commitment to establish a process to assess and analyze the capital needs of all taxing entities in Orleans Parish. When BGR released its report on the City’s capital program in November 1997, the City had not moved forward with this consolidated process. The same holds true today —nearly three years later.

On specific projects, the City administration has been proactive in facilitating the capital projects of other entities in New Orleans. Recent examples include the Regional Transit Authority’s Canal Streetcar Line and the Sewerage and Water Board’s extensive sewer rehabilitation program. The City administration has also sponsored capital contributions by the City to other entities — such as $12 million for the convention center in the 1995 bond package. Further, the administration has worked with the Criminal Sheriff for the Law Enforcement District’s bond proposal on the November 7 ballot. However, these ad hoc efforts do not systematically address inter-jurisdictional priorities for scarce tax dollars.

The competition for capital funding will be particularly keen in the near future. The City and the Law Enforcement District have bond proposals before the voters in November. The Orleans Parish Schools’ 1995 improvement program will wind up in the next two years, and the schools still have huge unmet capital needs. The Sewerage and Water Board will pursue additional capital funding for major drainage improvements and court-mandated sewer system rehabilitation in the next year or two. New federal drinking water standards will probably require more funding after that. The burden of paying for these proposals will fall on the same revenue base — the citizens and businesses of New Orleans.

Considering the high per capita debt and the aggregate level of unmet capital needs in New Orleans, any significant capital financing in New Orleans will be financially difficult. In the absence of a viable inter-jurisdictional capital planning process, the citizens of New Orleans have no assurance that their financial sacrifices will yield the most effective results.

Endnotes

1 The 1995 bond proposition authorized (but did not require) improvements to specific streets. At the same time, it did not limit funding to those streets. The City has generally adhered to the list of major street projects in the bond proposition.

2 City officials and consultants frequently cite lower debt service figures, but in doing so, they include only GO and limited tax bonds in the discussion. In addition to these species of debt, the city has incurred debt in the form of certificates of indebtedness, which will cost the City $16.9 million in 2000.

3 See U.S. Census Bureau tabulations, Statistical Abstract of the United States: 1999, p. 322.

4 Total calculated by BGR from the City's and Sewerage and Water Board's official bond statements, the City's 1999 Comprehensive Annual Financial Report, and payments schedules for existing local government bonds.

5 Debt data compiled from the City's and Sewerage and Water Board's official bond statements. The 1999 population (460,913) is from the U.S. Census population estimate for July 1, 1999. National average estimated by BGR by extrapolating 1990-1996 government finance data from U.S. Census Bureau to 1999. Raw data is available at www.census.gov/govs/estimate/96stlus.txt. The presentation of both local debt and the national average includes tax supported debt as well as revenue bonds.

6 Using the 1990 Orleans Parish population of 496,938, the per capita debt would be $3,141.

7 The City's total debt service exceeds $50 million (See Figure A). However, some of the debt service is a consequence of retirement system financing. The $50 million stated in the text is BGR's estimate of debt service that is attributable to capital improvement financing, including GO bonds, limited tax bonds, and a portion of the City's certificates of indebtedness.

For additional information on this report, please contact Patricia Morris, (504) 525-4152, x17, or via e-mail, pemorris@bgr.org.